1 Organization and Formatting
1.1 General (same as for other B-Sheets; follow this link for easy reference)
1.2 Sheet-Specific — Making it All Fit
Insert a graphical rendering of your Term-II Gantt chart showing as much detail as possible while maintaining legibly-sized text. If necessary (occasionally, but not often needed), roll-up (minimize) lower-level subtask details to preserve legibility.
2 Content Presentation
- There is no specific Page Input textbox/content to be addressed for this page.
- Like Term-I, this is presented as a Gantt chart, which should be produced in MS Project.
- At the Project Continuation Review (PCR) stage, the Term-II chart should include the following:
- from the Term-II task list, all main tasks as well as subtasks, focused on the remainder of the project (Term-II)
- from the adjusted/updated milestones list, all milestones falling in the Term-II timeframe
- task-to-task dependencies/connectivity
- There is no specific Page Output textbox/content to be addressed for this page.
3 Examples of Great Work
Do a great job and be the first!